Choosing between a 4- and a 5-section boom starts with the jobsite: where the truck-mounted pump can be positioned, the obstacles between the truck and the placing point, and the overhead clearance above the machine.
An extra section adds another joint, but the results depend on the overall boom geometry. The comparison therefore needs to take account of the model’s technical data sheet and actual working conditions.
This guide focuses on truck-mounted pump booms in the 30 to 40 metre range, where CIFA offers both 4- and 5-section configurations. It also explains how to read the working diagram and check unfolding clearances, presents three typical jobsite scenarios and highlights mistakes to avoid.
How to read the working diagram and check unfolding clearances before a pour
To establish whether your fleet needs a 4- or a 5-section boom, start with the technical data sheet and the truck’s actual position on site.
Follow these practical steps:
-
Mark the position where the machine can stand on the site plan, with its outriggers fully or partially extended.
-
Measure the horizontal distance and elevation of each placing point from the centre of the slewing axis, rather than from the edge of the truck.
-
Plot these points on the working diagram in the data sheet, which shows the area the end hose can reach and the net reach beyond the machine’s footprint.
-
Check the overhead clearance above the truck and compare it with the minimum unfolding height stated in the technical data sheet.
-
Map any obstacles along the route, recording their height and distance, and assess whether the boom will need to change direction to reach over them.
-
If the outriggers cannot be fully extended, check the reduced working envelope. On CIFA machines equipped with Smartronic, the MBE function calculates and displays the maximum permitted safe extension before the boom is unfolded.
If both configurations can reach all the placing points after these checks, the fifth section adds no further coverage. The comparison then shifts to other factors, such as outrigger configuration, truck wheelbase and weight. If only one configuration can negotiate an obstacle or unfold beneath a ceiling, however, you have identified the deciding factor for your purchase.
Jobsite examples
The following examples are illustrative scenarios designed to explain the reasoning. They do not describe actual customer projects and do not replace checks against the machine’s working diagram.
-
SCENARIO A: Placing concrete beyond a building. The slab to be poured is behind a two-storey building, and the pump can only stand on the road. The boom needs to rise above the roof and then descend towards the placing point. An additional joint may allow the final section to be positioned vertically over the pour, even close to the obstacle. The key measurements to check are the building’s height and the net distances involved.
In situations like this, the number of sections can determine whether the end hose reaches the placing point without repositioning the machine.
-
SCENARIO B: Placing concrete beneath a low roof. The pump needs to work beneath a canopy or inside an industrial building, with around 8 metres of overhead clearance above the truck. The first figure to compare is the minimum unfolding height. CIFA’s data sheets specify 8.4 m for the K36L and 7.03 m for the K36L-5. In this scenario, that difference determines whether the boom can unfold at all, before reach is even considered.
-
SCENARIO C: Placing concrete across large, open raft foundations. The pour covers a large raft foundation with no overhead obstructions, and the end hose needs to move continuously. Here, the number of sections matters less than net horizontal reach and smooth boom movement. A 4-section Z-folding boom can be well suited to this requirement.
Positioning the end hose and controlling it during a pour: two different capabilities
These are two distinct technical capabilities:
-
Positioning the end hose means bringing it to the placing point with the correct orientation. This depends on boom geometry, including the number and length of the sections, their angles and the folding system.
-
Controlling it during a pour means keeping it where it is needed as concrete arrives in pulses and the boom moves. This depends on structural stiffness, the mass at the boom tip, proportional controls and control functions.
A fifth section enhances the first capability. Other factors have a greater influence on the second, such as the ABC (Antibouncing) function available on Smartronic versions or the V-STOP system, which CIFA states reduce boom oscillation by up to 25%.
Design features that make the boom stiffer and more durable, such as through-pins, variable thicknesses, finite element structural analysis (FEM) and strength testing, apply to both 4- and 5-section booms. You can explore these features in our article on choosing a boom and when to consider carbon fibre.

Common mistakes when choosing the number of boom sections
-
More sections = better performance: assuming that adding sections automatically improves performance and efficiency.
-
Underestimating structural factors: attributing benefits to an extra section, such as the fifth or sixth, when they actually depend on the folding system (Z or RZ), material quality (special steels or carbon fibre) or chassis stability.
-
Ignoring jobsite obstacles: focusing only on overall length without considering the space occupied by the boom joints, the end hose’s final approach to the placing point, or the presence of ceilings or power lines.
-
Comparing different boom classes: comparing minimum unfolding heights across different boom classes rather than between models in the same range.
-
Overlooking road transport requirements: ignoring gross vehicle weight, compactness and travel between jobsites.
-
Taking technology for granted: assuming that advanced functions, such as automatic unfolding or boom bouncing control, are included without checking their compatibility with the selected boom model and pumping unit.
Checklist: choosing a boom with 4 or 5 sections
For each question, the right-hand column identifies the technical data to check against your answer.
| Operating scenario (question) | Technical specification to check |
| Are there obstacles between the pump and the placing point that the boom must reach over before descending? | Working diagram, articulation angles, number of sections |
| Do you frequently work inside industrial buildings, in tunnels or in spaces with restricted ceiling heights? | Minimum unfolding height of the model |
| Does the pour require continuous control of the end hose? | Control functions (ABC, Constant Height), mass of the final boom sections |
| How many setups are required each day? | Unfolding sequence and times, availability of automatic unfolding |
| Is it an urban jobsite with very limited space for outrigger deployment? | Outrigger type and footprint (telescopic vs swing-out), MBE and ASC safety functions |
| Which weight limits and road traffic regulations apply in the country of use? | Actual total weight of the complete machine, number of axles and wheelbase |
Making your choice with CIFA
In the 30 to 40 metre range, the fifth section addresses specific requirements for boom geometry and space. It is a choice driven by the types of jobsite you regularly work on, rather than a straightforward performance upgrade:
-
When to choose 5 sections: this is the ideal solution if you frequently need to reach over structures, work beneath roofs with limited overhead clearance or position the end hose in obscured locations that the less flexible paths of a 4-section boom cannot reach.
-
When to choose 4 sections: if most of your work involves direct paths to the placing point or standard reach requirements, a 4-section boom with Z-folding remains the benchmark for straightforward operation, low weight and cost optimisation.
For more detail, read our guide to the differences between 4- and 5-section booms on truck-mounted concrete pumps.
Information to share with the CIFA team for a feasibility study
To compare configurations and then specify the ideal machine, share the following information with the CIFA team:
-
Typical jobsite layout: working distances, placing elevations and the average height of obstacles to be cleared.
-
Height restrictions: the minimum overhead clearance encountered when setting up indoors.
-
Outrigger setup areas: the average space available for extending the outriggers.
-
Productivity: the average number of setup and pouring cycles per working day.
-
Pumping unit: your preference for an open- or closed-loop hydraulic circuit.
-
Type approval: weight limits and road traffic regulations in the country of registration.
Configure your machine online or contact CIFA directly. Using your data, we will check the working diagrams to establish whether the K36L, K36L-5 or another model in the range best suits your jobsites.
Frequently asked questions
-
When should you choose a 5-section boom?
When the jobsite has complex obstacles to reach over, restricted routes or limited overhead clearance, such as low ceilings, requiring both greater boom articulation and a lower minimum unfolding height. Check the latter in the model’s technical data sheet.
-
When is a 4-section boom sufficient?
When pours involve direct paths to the placing point or standard reach requirements, as with large, open raft foundations. In these cases, a 4-section Z-folding boom offers straightforward operation, low weight and cost optimisation.
-
Where should placing distances and elevations be measured from?
From the centre of the slewing axis, rather than the edge of the truck. Plot these measurements on the working diagram in the technical data sheet, which shows the area the end hose can reach and the net reach beyond the machine’s footprint.
-
Which specification should you check for work beneath a low roof?
The minimum unfolding height, compared with the overhead clearance above the truck. This varies by model. CIFA’s data sheets specify 8.4 m for the K36L and 7.03 m for the K36L-5.
-
How do you check the working envelope when the outriggers cannot be fully extended?
On CIFA machines equipped with Smartronic, the MBE function calculates and displays the maximum permitted safe extension before the boom is unfolded.