Truck mixer pumps: differences and when to choose one

Written by Cifa | Nov 27, 2026, 2:00:01 PM

An 8 m³ slab in a narrow town-centre street can be poured in two ways: using two vehicles, a truck-mounted concrete pump and the truck mixer supplying it, or a single truck mixer pump.

The deciding factors are how many vehicles the jobsite can accommodate, how much concrete is actually needed and how the working day is organised between pours.

Here we compare truck mixer pumps, truck-mounted concrete pumps and trailer pumps against the criteria that matter on the jobsite. We explain where a truck mixer pump is most effective, when another solution makes more sense and what CIFA offers.

 

Truck mixer pump, truck-mounted concrete pump or trailer pump: what changes on the jobsite?

A truck mixer pump carries and pumps concrete from the same truck chassis. A truck-mounted concrete pump is dedicated to pumping and receives concrete from truck mixers. A trailer pump remains in a fixed position and pushes concrete through a pipeline.

The main difference is in the logistics.

Aspect Truck mixer pump Truck-mounted concrete pump Trailer pump
Vehicles on site  One vehicle that carries and pumps concrete The pump and a steady succession of one or more truck mixers The pump, truck mixers and pipeline
Concrete supply The machine’s own drum Truck mixers Truck mixers
Concrete placement
On-board boom On-board boom (including very long booms) Ground- or wall-mounted pipeline (no on-board boom)
Pour continuity
Limited by drum capacity Maintained by a steady succession of truck mixers Maintained by a steady succession of truck mixers
Space required
One vehicle to set up on stabilisers Pump set up on stabilisers, plus manoeuvring space for truck mixers Compact machine, plus space to lay the pipeline

 

With a truck mixer pump, the pour stops when the drum is empty. With a truck-mounted concrete pump, continuity depends on truck mixer arrivals. This is an advantage for large volumes, but adds cost on smaller pours, as more vehicles and people are needed for just a few cubic metres.

(The other two solutions are covered in more detail in our articles on truck-mounted concrete pumps and trailer pumps.)