Choosing between a 4- and a 5-section boom starts with the jobsite: where the truck-mounted pump can be positioned, the obstacles between the truck and the placing point, and the overhead clearance above the machine.
An extra section adds another joint, but the results depend on the overall boom geometry. The comparison therefore needs to take account of the model’s technical data sheet and actual working conditions.
This guide focuses on truck-mounted pump booms in the 30 to 40 metre range, where CIFA offers both 4- and 5-section configurations. It also explains how to read the working diagram and check unfolding clearances, presents three typical jobsite scenarios and highlights mistakes to avoid.
To establish whether your fleet needs a 4- or a 5-section boom, start with the technical data sheet and the truck’s actual position on site.
Follow these practical steps:
Mark the position where the machine can stand on the site plan, with its outriggers fully or partially extended.
Measure the horizontal distance and elevation of each placing point from the centre of the slewing axis, rather than from the edge of the truck.
Plot these points on the working diagram in the data sheet, which shows the area the end hose can reach and the net reach beyond the machine’s footprint.
Check the overhead clearance above the truck and compare it with the minimum unfolding height stated in the technical data sheet.
Map any obstacles along the route, recording their height and distance, and assess whether the boom will need to change direction to reach over them.
If the outriggers cannot be fully extended, check the reduced working envelope. On CIFA machines equipped with Smartronic, the MBE function calculates and displays the maximum permitted safe extension before the boom is unfolded.
If both configurations can reach all the placing points after these checks, the fifth section adds no further coverage. The comparison then shifts to other factors, such as outrigger configuration, truck wheelbase and weight. If only one configuration can negotiate an obstacle or unfold beneath a ceiling, however, you have identified the deciding factor for your purchase.
The following examples are illustrative scenarios designed to explain the reasoning. They do not describe actual customer projects and do not replace checks against the machine’s working diagram.
SCENARIO A: Placing concrete beyond a building. The slab to be poured is behind a two-storey building, and the pump can only stand on the road. The boom needs to rise above the roof and then descend towards the placing point. An additional joint may allow the final section to be positioned vertically over the pour, even close to the obstacle. The key measurements to check are the building’s height and the net distances involved.
In situations like this, the number of sections can determine whether the end hose reaches the placing point without repositioning the machine.
SCENARIO B: Placing concrete beneath a low roof. The pump needs to work beneath a canopy or inside an industrial building, with around 8 metres of overhead clearance above the truck. The first figure to compare is the minimum unfolding height. CIFA’s data sheets specify 8.4 m for the K36L and 7.03 m for the K36L-5. In this scenario, that difference determines whether the boom can unfold at all, before reach is even considered.
SCENARIO C: Placing concrete across large, open raft foundations. The pour covers a large raft foundation with no overhead obstructions, and the end hose needs to move continuously. Here, the number of sections matters less than net horizontal reach and smooth boom movement. A 4-section Z-folding boom can be well suited to this requirement.